|
| Issues | Comments |
| Collapse Zones | The Santana Row complex quickly became fully
involved and posed a significant potential for
collapse. The incident commander established a
collapse zone around the perimeter of the complex
and removed personnel and apparatus out of
harms way.
|
| Communications | The initial incident rapidly progressed to five
alarms and flying embers ignited a number of
buildings downwind that ultimately developed
into a separate, six alarm blaze. The two incidents
generated a very heavy volume of radio
traffic, which is common during large-scale
incidents, and quickly overtaxed the city’s radio
system. |
| Concurrent Incidents | Within a two-hour period, the San Jose Fire
Department was confronted with two large-scale
events that would over tax the capabilities of all,
but the largest of fire departments. During these
two events, the Department also responded to
twelve EMS calls and four fires, which included a
fire on the roof of a high-rise building that had
been ignited by the flying embers from the
Santana Row fire. |
| Construction |
The building of origin covered approximately six
acres and included six floors and a basement.
Each floor contained approximately 225,000
square feet. The basement and the first two floors
were constructed of reinforced concrete. The outer perimeters of the first two levels were to
have been used for retail purposes and the
remainder as parking. A third, but smaller,
level for parking was built upon the top of the
parking structure. Additionally, there were five
separate, wood-frame residential structures,
three stories in height. The majority of the
structures did not have sheet-rock installed at
the time of the fire.
|
| Exposures |
The fire spread to the Huff/Moorpark area
when burning embers from the Santana Row
fire became airborne and ignited a number of
wooden roofs in the neighborhood, which was
approximately one-half mile down wind.
|
| Incident Management | A system for managing large-scale incidents
must be in place and used in order to successfully
manage incidents of this magnitude. The
system should include provisions for the
accountability of personnel and their continuing
safety. |
| Fire Suppression Systems | Upon completion, the complex would have
been fully sprinklered, but the systems were
not operational at the time of the fire. |
| Mutual Aid/Automatic Aid | San Jose has a number of automatic aid agreements
with its neighbors and automatic aid was
included in the assignments to the Santana
Row fire. Mutual aid agreements exist, but are
more problematic because all mutual aid companies must be dispatched manually because
they are not programmed into the City’s
CAD system. |
| Pre-Incident Planning | Planning is essential in the management of a
large-scale incident, which involves resources
from multiple jurisdictions and that requires the
interaction of multiple agencies. |
| Resources | The Santana Row fire required the commitment
of 119 firefighters and thirty-one pieces of
apparatus. The Huff/Moorpark fire required the
commitment of 102 firefighters and thirty-four
pieces of apparatus. Additional apparatus and
personnel were required to respond to the
sixteen incidents that occurred during the event
as well as maintaining a reserve to ensure
protection for the city while the incidents were
brought under control. |
| Time of Day | The two multiple alarm blazes occurred during
the middle of the afternoon, which resulted in
the early detection of both incidents and may
have prevented injuries and the loss of life that
could have occurred had the fire occurred
during the night when the residents of the Huff/
Moorpark area may have been asleep. However,
the incidents contributed to congestion of
the afternoon rush hour that not only inconvenienced
motorists, but potentially delayed the
arrival of the multiple alarm companies. |
Next » The Community
|